29.9 C
Lagos
Monday, November 25, 2024

How over N11tr for electricity was squandered under OBJ, Yar’Adua, Jonathan -SERAP

Must read

Source: www.serap-nigeria.org
A new report by the Socio-Economic Rights and Accountability Project (SERAP) has revealed how over N11 trillion meant to provide regular electricity supply was allegedly squandered under the governments of former presidents Olusegun Obasanjo, Umaru Musa Yar’Adua and Goodluck Jonathan.
 
According to the report, “The total estimated financial loss to Nigeria from corruption in the electricity sector starting from the return to democracy in 1999 to date is over Eleven Trillion Naira (N11 Trillion Naira). This represents public funds, private equity and social investment (or divestments) in the power sector. It is estimated that may reach over Twenty Trillion Naira (N20 Trillion Naira) in the next decade given the rate of Government investment and funding in the power sector amidst dwindling fortune and recurrent revenue shortfalls.”
 
The 65 pages report launched today at the Westown Hotels, Lagos is titled: From Darkness to Darkness: How Nigerians are Paying the Price for Corruption in the Electricity Sector. The report presented to the media bypresented by Yemi Oke, Ass. Professor, Energy/Electricity Law, Faculty of Law, University of Lagos discloses that “the country has lost more megawatts in the post-privatisation era due to corruption, impunity, among other social challenges reflected in the report.”
 
The report shows that, “The much-publicised power sector reforms in Nigeria under the Electric Power Sector Reform Act of 2005 is yet to yield desired and/or anticipated fruits largely due to corruption and impunity of perpetrators, regulatory lapses and policy inconsistencies. Ordinary Nigerians continue to pay the price for corruption in the electricity sector–staying in darkness, but still made to pay crazy electricity bills.”
 
Mr Femi Falana SAN who chaired the report launch said that, “This report is a must read, and I promise to lead in the follow-up litigation efforts to ensure the full implementation of the recommendations of the report.”
 
The report launch was also attended by Babatunde Irukera, the Director General/Chief Executive of the Consumer Protection Council (CPC); and Mr Ibrahim Magu Chairman Economic and Financial Crimes Commission (EFCC) who was represented by Mr Osita Nwajah, Director Public Affairs EFCC. Both promised to work to ensure the full implementation of the recommendations contained in the report.
 
Others at the events are Barrister Babatunde Ogala; Dayo Olaide, Deputy Director Macarthur Foundation; Eva Kouka, Program Officer Ford Foundation; Motunrayo Alaka Coordinator Wole Soyinka Centre for Investigative Journalism; representatives of the Independent Corrupt Practices and other Related Offences Commission (ICPC);the National Human Rights Commission, and the media.
 
The report accuses Dr. Ransom Owan-led board of the Nigerian Electricity Regulatory Commission (NERC) of allegedly “settling officials with millions of Naira as severance packages and for embarrassing them with alleged Three Billion Naira (N3,000,000,000.00) Fraud. The authorities must undertake a thorough, impartial and transparent investigation as to the reasons why corruption charges were withdrawn, and to recover any corrupt funds.”
 
The report also called for the reopening and effective prosecution of corruption allegations, including the alleged “looting of the benefits of families of the deceased employees of Power Holding Company of Nigeria (PHCN) levelled against a former Permanent Secretary in the Ministry of Power, Godknows Igali”
 
The report reads: “The Obasanjo’s administration spent $10 billion on NIPP with no results in terms of increase in power generation. $13.278,937,409.94 was expended on the power sector in eight years while unfunded commitments amounted to $12 billion.”
 
“The Federal Government then budgeted a whopping N16 billion for the various reforms under Liyel Imoke (2003 to 2007) which went down the drains as it failed to generate the needed amount of electricity or meet the set goals. Imoke was alleged to have personally collected the sum of $7.8 million for the execution of the contract for the construction of the Jos-Yola Transmission Line, which was never executed. There were documented/reported allegations of corruption against Imoke that fizzled-out shortly thereafter.”
 
“Professor Chinedu Nebo handed over the assets of the PHCN to private investors on November 1, 2013. Prof. Nebo is alleged to have corruptly funded the privatized power sector with over N200 Billion despite privatization. The allegation of N200 Billion funding of the privatized power sector during Prof Nebo’s tenure should be thoroughly and transparently investigated and anyone suspected to be responsible prosecuted. Any corrupt funds should be fully recovered.”
 
“Our research revealed that the sum of N1.5 billion with which the vehicles were acquired was allegedly sourced from the diverted N27 billion insurance premium of deceased workers of the defunct Power Holding Company of Nigeria (PHCN).”
 
“The National Assembly and members should desist from and avoid manipulating the award of electricity contracts or cite projects in their constituencies under the guise of “Constituency Project”. The National Assembly should publish and ensure the full implementation of the recommendations of all power-related investigations to date.”
 
“The Federal Government should back-down from Rural Electrification initiatives and allow States to undertake rural electrification through their respective Local Governments and Development Areas. Federal Government should consider fully divesting its stakes in the power sector and allow for efficient, decentralized sector governance by Federal and State governments, as appropriate, in line with the provisions of the Second Schedule, paragraph 13 and 14 of the Constitution of the Federal Republic of Nigeria 1999 (as amended).”
 
“The 36 state governments should wake up to their rights, duties and obligations under the Constitution of the Federal Republic of Nigeria relating to the power sector by working to promote and ensure access to regular and uninterrupted electricity supply for all residents within their states. The 36 state governments have been abdicating the duties to the power sector, bearing in mind that Power is an item on the Concurrent Legislative List under the Nigerian Constitution 1999 (as amended).”
 
“When the late Bola Ige took up the mantle of the Power and Steel Ministry in 1999, he probably didn’t understand the magnitude of problems in the power sector and consequently, promised that within six months of his appointment, “power failure will be a thing of the past” and that on a regular basis, he will brief the nation on the state of power, steel and aluminum. Current minister Babatunde Fashola SAN also claimed that ‘a serious Government will fix the power problem in six months’”
 
“The power sector under Ige was characterized by epileptic and unreliable supply, bogus billing and archaic rate collection. The late Minister failed and was unable to put an end to these. His failure was attributed to acts of sabotage and corruption by people who were benefitting from the use of generators. The late Bola Ige was not accused of corruption.”
 
“When Rilwan Lanre Babalola (2008 to 2010) took over the affairs in the Ministry of Power, he met 3,700MW on ground and promised to increase it to 6,000MW and ensure a 24-hour power supply by the end of 2009. Six months after assuring Nigerians of making a significant impact in the sector, in September 2009, the 3,700MW capacity he met on ground dropped to 2,710MW which shortfall was attributed to inadequate supply of gas to the new generators.”
 
“The duo, Elumelu and Ugbane allegedly colluded in misappropriating over N10 billion public funds from the account of Rural Electrification Agency (REA). The research also established, based on evaluation and analyzing documents, a prima-facie case of misappropriation of unspent funds at the end of the year instead of returning same to the treasury. Alleged misappropriation of N500million to buy houses; diversion of REA’s funds; flouting of government’s rules on award of contracts and award of fictitious and unnecessary contracts without following due process.”
 
“The government of Nigeria handed over the transmission company to a Canadian company Manitoba, to manage and under a management service contract of over $200 million. Findings also show that the Transmission Company of Nigeria could not execute most of its approved 44 projects after having 50 percent of its N30 billion 2016 budget released to it. Funds were released from Eurobond. $23.6 million allegedly paid to Manitoba Hydro International (MHI) of Canada to manage the Transmission Company of Nigeria (TCN) would appear to be without due process.”
 
“The privatization of PHCN would appear to have yielded the country total darkness. Gains of privatization were lost through alleged corruption, manipulation of rules and disregard to extant laws and lack of transparency in the exercise. The PBE encouraged the deferment of payment and restructuring of payment terms in contravention of bidding rules to the disadvantage of other bidders.”
 
“Billing methodology shrouded in secrecy. Billings do not reflect actual electricity consumptions in most cases. Most if not all, officials of the DISCOs are still very corrupt and demand gratification from customers before doing the job they are paid to do. Grand corruption against the Federal Government owner of the 40% stakes in the DISCOS, and by implications, the Nigerian masses due to non-remittance or under-remittances of the monies collected by the DISCOs.”
 
“The Manitoba deal is shrouded in secrecy as essential details of the deal remain unknown to Nigerians till date. The authorities should undertake a public-oriented audit on the state of affairs of the TCN two years before and after the Manitoba deal. The outcome of the audit should form basis for further action and charges in court against the suspected perpetrators and corrupt funds fully recovered.”
 
“The Federal Government should undertake a thorough, impartial and transparent investigation into the power sector privatization with a view to doing things the right, fair and just way. Ownership of public stakes of 40% in those entities should be revisited and further privatized to avoid using government/public resources to subsidize private entities.”
“Attention should be focused also on petty corruption. Petty corruption in the electricity sector has not received much attention, as the focus has been on grand corruption in the sector.”
“The Attorney-General of the Federation and Minister of Justice Abubakar Malami SAN should request the report of the House of Representative Committee that probed government spending in the power sector from 2000 to 2007, and the Elumelu House Probe Committee which had accused 21 persons and 36 companies of subversion of government policy on due process make the report public and ensure appropriate legal action against anyone suspected to be involved in corruption as well as full recovery of corrupt funds.”
“Undocumented, monumental fraud and corruption is said to be perpetrated at the Niger Delta Power Holding Company (NDPHC) and investigation by the EFCC and ICPC will ensure that those involved are effectively brought to justice.”
“Mr Malami should direct the EFCC and ICPC to probe metering and billing fraud and corruption and bribery among Discos. Most consumers are unhappy will their billing methodology and feel short-changed by the operators. Mr Malami should promptly make progress on all outstanding cases of corruption in the electricity sector including by ensuring effective prosecution of all power sector cases being handled by the Ministry.”
“The ICPC should make public the status of the investigation and recommendations for prosecution (if any) on the AEDC Recruitment Scandal/Jumbo Pay Scandal given the facts that the Nigerian Government and public have 40% stakes in the AEDC. The Manitoba deal is shrouded in secrecy as essential details of the deal remain unknown to Nigerians till date. The EFCC/ICPC should lead a public-oriented audit on the state of affairs of the TCN two years before and after the Manitoba deal.”
“The ICPC show tell Nigerians about the current status of the probe of the recruitment scandal and corruption-induced jumbo pay to workers of the Abuja Electricity Distribution Company (AEDC Plc). Anyone found to be responsible should be brought to justice and corrupt funds fully recovered.”

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Related articles